Well now, let me start with Monday 26th - the rest of the bison slabs were delivered and that's where things started going wrong. The clever lorry driver managed to reverse into the scaffolding in front of the family room, then push it into the brickwork resulting in the front wall being pushed in. It has now to be knocked down and rebuilt (see below picture).

The weather didn't help progress this week, but what else can you expect at this time of year! Hopefully it will settle again soon and the brickies can get on full speed ahead with their impressive work. See below photographs for this weeks progress.
KYLE CARRIES OUT STRUCTIAL ENGINEERING INSPECTION
BUT MUM, MY ROOM IS TIDY COME UP AND SEE
THIS WEEKS BUILDING PROGRESS SHOWN BELOW